CONTRACTS LET FOR HAZEN AND STILLWATER STRUCTURES TO FERNLEY MAN.
At a joint meeting of the Boards of School Trustees of Stillwa ter and Hazen school districts held Wednes day in the court house for the purpose of awarding the contract for the building of public schools, it was unanimously decided to place con, struction of the two buildings in the hands of contractor Olson of Fernley, lie being in both cases the lowest bidder.
The Hazen contract calls for the erection of a modern three room building of concrete to cost approximately $5,400.00, while the Stillwate building will be a duplicate
in plan but will be a frame building and will cost about $4,800.00. Plans and specifications for both buildings were made by architect William Mallis of Fallon. Construction will be begun at once and both buildings will be ready for occupancy when school opens in September.
There were present at the meeting Trustees Conrad, Frey, and Dalton of Stillwater, Trustees Pyle and Dobbs of Hazen, Architect Mallis, Attorney Cann, and Superintendent McCracken.
In view of the difficulty of securing contractors' figures within the bond issues under present market conditions. the boards are to be congratulated upon this happy solution of what might have been a perplexing problem.

Creator

Churchill County Eagle

Source

Churchill County Recorders Office

Publisher

Churchill County Museum

Date

6.9.1917

Contributor

Churchill County Museum

Format

Newspaper, jpeg, pdf, text

Language

English

Type

Newspaper, jpeg, pdf, text

Identifier

Churchill County Eagle 6.9.1917 NEw School Building

Coverage

Hazen Nevada

Text Item Type Metadata

Text

CONTRACTS LET FOR HAZEN AND STILLWATER STRUCTURES TO FERNLEY MAN.
At a joint meeting of the Boards of School Trustees of Stillwa ter and Hazen school districts held Wednes day in the court house for the purpose of awarding the contract for the building of public schools, it was unanimously decided to place con, struction of the two buildings in the hands of contractor Olson of Fernley, lie being in both cases the lowest bidder.
The Hazen contract calls for the erection of a modern three room building of concrete to cost approximately $5,400.00, while the Stillwate building will be a duplicate
in plan but will be a frame building and will cost about $4,800.00. Plans and specifications for both buildings were made by architect William Mallis of Fallon. Construction will be begun at once and both buildings will be ready for occupancy when school opens in September.
There were present at the meeting Trustees Conrad, Frey, and Dalton of Stillwater, Trustees Pyle and Dobbs of Hazen, Architect Mallis, Attorney Cann, and Superintendent McCracken.
In view of the difficulty of securing contractors' figures within the bond issues under present market conditions. the boards are to be congratulated upon this happy solution of what might have been a perplexing problem.

Original Format

Newspaper

Files

https://s3.amazonaws.com/omeka-net/45840/archive/files/c94ad14bdabb185b871900500001076a.pdf
https://s3.amazonaws.com/omeka-net/45840/archive/files/30f0d3a9dfa60ad196574635e351de60.jpg

Citation

Churchill County Eagle, “Contracts Let For Hazen and Stillwater Structures,” Churchill County Museum Digital Archive: Fallon, Nevada, accessed April 27, 2024, https://ccmuseum.omeka.net/items/show/525.

Comments